Summary Report of the 493rd RSK Meeting
26.04.2017

The RSK was informed about the evaluation of the operating reports of the nuclear power plants of 2014. Furthermore, the consultation results of a working group on the flaws in the reactor pressure vessels of the Belgian nuclear power plants Doel-3 and Tihange-2 detected during ultrasonic inspections (Ultraschallanzeigen in den Reaktordruckbehältern (RDB) der belgischen Kernkraftwerke Doel-3 und Tihange-2) were discussed. The consultation on the statement on the evaluation of the implementation of RSK recommendations in response to Fukushima (Bewertung der Umsetzung von RSK-Empfehlungen im Nachgang zu Fukushima) for the German BWR plants was started.