Summary Report of the 469th RSK Meeting
22.10.2014

The consultation on the statements on section-wide unavailabilities due to electrical coupling between redundant sections of the emergency power system of German nuclear power plants and on neutron flux oscillations, deformations of fuel assemblies, damage to cladding tubes, spacers, hold-down springs and alignment pins were started. The draft statement on inspection methods for installation and installation situation of anchors and ensuring the required load transfer was referred to the Committee on PRESSURE-RETAINING COMPONENTS AND MATERIALS (DKW) for revision.